| Client
contacts innovaHouse Ltd
|
- We
discuss design ideas, living requirements and decide
on technical specifications
|
- Preliminary
drawings are provided by innovaHouse architect
|
- innnovaHouse
provide client with a written estimate
|
- Acceptance
and approval of drawings required from client
|
- InnovaHouse
and client meeting to view site, signature of contract
and Client Stage 1 payment of 10% upon signature
|
- InnovaHouse
architect to prepare drawings for Building Warrant
and Structural Calculations
|
- Building
Warrant application submitted to local planning
office
|
|
|
- Client
Stage 2 payment of 20% upon BW approval
|
- innovaHouse
arrange safety fencing to site and risk assessment
|
- Commencement
of production with German manufacturer
|
PROJECT
BUILD COMMENCES |
WEEKS
1 - 4
- Commencement
of foundations (allow 4 weeks, weather permitting)
|
- Foundations
checked and drainage pressure tested by Building
Control
|
WEEK
5
- Delivery
of House parts, crane to site
|
- Client
Stage 3 payment of 25% upon delivery
|
- Erection
of house to wind and watertight stage (within 5-7
days)
|
WEEK
6
- Client
Stage 4 payment of 20% upon completion of
wind and watertight
|
WEEK
7
- Commencement
of internal works
|
WEEK
14
- Client
Stage 5 payment of 20% upon commencement of internal
works to completion
|
WEEK
15
- Preparation
of access to house (landscaping and gardening an
additional cost, decided at time of contract signature)
|
WEEK
16
- Turnkey
and handover to Client
|
- Client
Stage 6 payment of 5% upon handover to Client
|
WEEK
18
- Completion
Certificate passed to Client
|
- 2
year After-Care Service
|